Two Months

After weeks of what seemed like slow progress, things are cranking along again. The structural steel to support the second floor office and locker room arrived Friday and will be installed Monday. The range ceiling supports have been installed, and…

The First Pour

We had all of the footings poured Thursday. The single-digit temps Thursday night into Friday prevented us from pouring the new floor. Looks like next week will be warmer, so that’s a good thing all around.

Footings and FFLs

Lots of heavy work this week. We got everything we needed from the structural engineer. The big question was how to support new walls and the new second floor as it became clear that the building was built on pilings…